Production Schedule

1.WED FEB 23
-Dwg Plan
-Render Setup

2.THU FEB 24
-Dwg Plan
-Render Exterior 1

3.FRI FEB 25
-Dwg Plan
-Render Exterior 2

4.SAT FEB 26
-Dwg Site Plan
-Render Exterior 3

5.SUN FEB 27
-Dwg Elevations
-Render Interior 1
-Render Interior 2

6.MON FEB 28
-Dwg Sections
-Render Interior 3
-Render Interior 4

7.TUE MAR 1
-Diagrams
-Final Text

8.WED MAR 2
-Layout Boards
-Supplementary Documents (Program Spreadsheet?)

9.THU MAR 3
-Print/Mount

10.FRI MAR 4
-Pack/Ship

Saturday, December 18, 2010

Working Schedule

START: January 10,2011
POST BOARDS: March 4, 2011 (8 weeks)
POST MODEL: March 18, 2011 (+2 weeks)

WEEK 1 (JAN 10) DOCUMENTATION AND CONCEPT
-Program Documentation
-Site Documentation
-Massing Studies
-Conceptual Intent Studies
>Base Documents Done

WEEK 2 (JAN 17) CONCEPT
-Formal Concept Study
>Conceptual Intent Done

WEEK 3 (JAN 24) DESIGN
-Public Circulation
-Curatorial Circulation
-Service Circulation
>Formal Concept Done

WEEK 4 (JAN 31) DESIGN
-Layout Studies
-Site Circulation
-Facade
-Materials
>Massing Done

WEEK 5 (FEB 7) DESIGN
-3D Model
>Layout Done

WEEK 6 (FEB 14) PRODUCTION
-Renderings
-Text
-Board Layouts
>Presentation Outline Done

WEEK 7 (FEB 21) PRODUCTION
-Renderings
-Drawings
>Renderings Done

WEEK 8 (FEB 28) PRODUCTION / DELIVERY
-Drawings
>Drawings Done
>Print, Pack, Post Boards

WEEK 9 (MAR 7)
-Site Model
-Model Material Studies
>Site Model Done

WEEK 10 (MAR 14) PRODUCTION / DELIVERY
>Final Model Done
>Pack, Post Model Done

Saturday, December 11, 2010

Due Dates

Postmarked by:

MARCH 4: Boards/A3 Printouts/CD
MARCH 18: Model